Next Contractors Meeting

Monday, June 18th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Hill Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.
  • The project will keep 2 of these 3 side streets open for the duration of the project.
    • Catlin Avenue
    • Lamborn/Grand Avenue
    • Hammond Avenue
  • Current Side Street Closures
    • Clough Avenue South
    • Lamborn/Grand South          Opening Monday 6/18/18
    • Baxter Avenue South
    • Cumming Avenue South
    • Hammond Avenue South      Closing Monday 6/18/18
    • Hughitt Avenue South
    • John Avenue South

Work completed since last update:

  • Pavement Removal
  • Water Main complete to Hammond Avenue.
  • Storm Sewer complete to Baxter Avenue.
  • Concrete Paving
    • Clough Avenue to Lamborn Avenue
    • Lamborn Avenue South
    • Grand Avenue South
  • Concrete Sidewalk: Catlin Avenue – Fisher Avenue
  • Asphalt Paving –
    • Burger King Parking Lot
    • Pilgrim Lutheran Church Parking Lot

Anticipated work schedule for next week:

  • Continue with water main installation
  • Continue with storm sewer installation
  • Concrete Curb and Gutter
  • Concrete Sidewalk
  • Continue work on the UW-Superior signs
  • Landscaping 2017 Project

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/