Next Contractors Meeting

MondaySeptember 25, 1:00 pm at the SBID Office, 823 Belknap St., Ste. L-10. (Lower level) 


Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control

  • Miscellaneous Construction    8/29/17 – 10/20/17   Traffic on the inside lanes to allow work from the outside lanes.

                              
Birch Avenue to Hill Avenue (East End)                          Traffic Control
North Side Construction        8/24/17 – 10/16/17   Bidirectional on the south side.
Median Construction             10/16/17 – 11/17/17  Traffic in the outside lanes.

Traffic impacts:

  • West End Lane Closures – be aware that lane closures of both inside and outside lanes will occur on and off over the next two weeks as landscaping, sign placement, pavement marking and other construction activities occur as we finish up this end of the project.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Concrete Work
    • Street lights
  • East End – Birch Avenue to Hill Avenue
    • Grading and Gravel

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Landscaping
    • Sign Placement
    • Tower Avenue median
  • East End – Birch Avenue to Hill Avenue
    • Concrete Pavement
    • Curb & Gutter

Next Contractors Meeting

Monday, September 25, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/