Next Contractors Meeting

Monday, October 9, 1:00 pm at the SBID Office,823 Belknap St., Ste. L-10. (Lower level) 

Project Staging, Schedule and Traffic Overview:
Banks Avenue to John Avenue (West End)                      Traffic Control
Miscellaneous Construction    8/29/17 – 10/20/17   Traffic on the inside lanes to allow work from the outside lanes.
                              
Birch Avenue to Hill Avenue (East End)                          Traffic Control
North Side Construction        8/24/17 – 10/20/17   Bidirectional on the south side.
Median Construction            10/20/17 – 11/17/17  Traffic in the outside lanes.

Traffic impacts:

  • West End Lane Closures – be aware that lane closures of both inside and outside lanes will occur on and off over the next two weeks as landscaping, sign placement, pavement marking and other construction activities occur as we finish up this end of the project.
  • East End Side Road Closures – Many side roads on the north side of the project are closed to allow for work on the curb, gutter and base this week.
  • Project Detours
    • There is a signed truck detour utilizing the City of Superior Truck Route.
    • There is an alternative detour route signed for other traffic to bypass the project.

Work completed since last update:

  • West End – Banks Avenue to John Avenue
    • Sign Placement
  • East End – Birch Avenue to Hill Avenue
    • Mainline Concrete Pavement

Anticipated work schedule for next week:

  • West End – Banks Avenue to John Avenue
    • Landscaping
    • Preformed Crosswalks
    • Tower Avenue median
  • East End – Birch Avenue to Hill Avenue
    • Curb & Gutter
    • Side Road Asphalt Pavement
    • Concrete Sidewalk

Next Contractors Meeting

Monday, October 9, 1:00 pm in the conference room at the Superior BID Office, 823 Belknap St., Ste. L-10. (Lower level) 

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/