Next Contractors Meeting

Monday, April 2nd, 1:00 pm at the Wisconsin Department of Transportation Office
(1701 N. 4th Street)

Description:  Belknap Street (USH 2) will be reconstructed from Banks Avenue to Hill Avenue over two constructions seasons. Work completed in 2017 included the west and east ends of the project from Banks Avenue to John Avenue and Birch Avenue to Hill Avenue respectively. The center section from John Avenue to Birch Avenue will be reconstructed in 2018.

Traffic impacts:

  • Single lane closures.

Work completed since last update:

  • 2018 Work Completed
    • Initial pavement saw cutting.

Anticipated work schedule for next week:

  • Continue with work on temporary signals.
  • Continue detour and alternative route signing.
  • Begin pavement removal.

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/