Next Contractors Meeting

Monday, July 30th, 1:00 pm at the SBID Office
(823 Belknap Street, Ste. L-10)

Traffic impacts:

  • USH 2/Belknap Street – Single lane closures from Mortorelli Avenue to Ogden Avenue.
  • Signed truck detour and alternate route available to bypass project.
  • Current Side Street Closures
    • North Side
      • Weeks Avenue
      • Fisher Avenue
      • Catlin Avenue
    • South Side
      • Clough Avenue South
      • Baxter Avenue South
      • Cumming Avenue South
      • Hammond Avenue South
      • Hughitt Avenue South
      • John Avenue South

Work completed since last update:

  • South Side (John Avenue to Grand Avenue)
    • Concrete Pavement
  • North Side (Weeks Avenue to Catlin Avenue)
    • Water Main
    • Fisher Avenue Storm Sewer

Anticipated work schedule for next week:

  • South Side (John Avenue to Grand Avenue)
    • Asphalt Paving Side Streets
    • Concrete Curb and Gutter
    • Concrete Sidewalk
    • Continue to work on Traffic Signals and Street Lighting
    • Continue work on the UW-Superior signs
    • Continue work on columns and walls
    • Landscaping
  • North Side (Weeks Avenue to Catlin Avenue)
    • Weeks Avenue Storm Sewer
    • Placing gravel from Catlin Avenue moving west

For additional information about the project, please visit the project website:http://projects.511wi.gov/belknap/